PRINCE2 Foundation Practice

Practice 60 PRINCE2 Foundation questions covering principles, themes, processes, roles, management products, risk, change, quality, and tailoring.

Level: PRINCE2 Difficulty: intermediate 60 questions 60 min
Answer each PRINCE2 question, choose or type your answer, then review the explanation. Wrong answers are saved locally for review.
Day streak: 0 days Saved only on this device
Progress 0 / 60
Question 1

How many principles does PRINCE2 define?

Select an answer
Question 2

Which statement best describes the continued business justification principle?

Select an answer
Question 3

According to PRINCE2, where is the business justification documented?

Select an answer
Question 4

Which principle requires roles and responsibilities to be defined before a project starts?

Select an answer
Question 5

The principle manage by stages means that the project board controls progress by reviewing which product?

Select an answer
Question 6

Which PRINCE2 principle means a project should be adapted to its environment, size, and risk level?

Select an answer
Question 7

Which principle encourages capturing lessons from previous work and using them during the project?

Select an answer
Question 8

Which theme defines how the project will be justified and funded?

Select an answer
Question 9

Which theme describes the roles and responsibilities of the project management team?

Select an answer
Question 10

Which theme covers how quality is planned, controlled, and verified?

Select an answer
Question 11

Which theme provides the basis for planning and controlling the project?

Select an answer
Question 12

Which theme deals with uncertainty and its effect on project objectives?

Select an answer
Question 13

Which theme manages requests for change, off-specifications, and problems?

Select an answer
Question 14

Which theme measures actual progress against tolerances and plans?

Select an answer
Question 15

Which process starts the project and produces the project brief?

Select an answer
Question 16

Which process produces the project initiation documentation?

Select an answer
Question 17

Which process gives the project board the authority to make key decisions?

Select an answer
Question 18

Which process authorizes work packages and monitors stage progress?

Select an answer
Question 19

Which process controls the work of team managers and ensures products meet specifications?

Select an answer
Question 20

Which process reviews the current stage and prepares the next stage plan?

Select an answer
Question 21

Which process verifies acceptance and recommends project closure?

Select an answer
Question 22

Who chairs the project board and owns the business case?

Select an answer
Question 23

Which role represents the interests of those who will use the project products?

Select an answer
Question 24

Which role represents those who provide resources and expertise to the project?

Select an answer
Question 25

Which role provides independent assurance that the project continues to meet the project board expectations?

Select an answer
Question 26

Which role provides administrative services such as maintaining registers and producing reports?

Select an answer
Question 27

Which role is accountable for managing the project on a day-to-day basis within tolerances set by the project board?

Select an answer
Question 28

Which role coordinates the work needed to deliver a work package?

Select an answer
Question 29

What is the primary purpose of the project initiation documentation?

Select an answer
Question 30

Which register records threats and opportunities affecting the project?

Select an answer
Question 31

Which register records requests for change, off-specifications, and problems or concerns?

Select an answer
Question 32

Which document is used to capture lessons during the project?

Select an answer
Question 33

Which report gives the project board a summary of stage progress at regular intervals?

Select an answer
Question 34

Which report is produced at the end of each stage for the project board?

Select an answer
Question 35

Which plan is created when a stage or project is forecast to exceed its agreed tolerance?

Select an answer
Question 36

Which plan describes how a team manager will deliver the work in a work package?

Select an answer
Question 37

What does a checkpoint report summarize?

Select an answer
Question 38

Which type of issue is a request to change a baselined product?

Select an answer
Question 39

Which type of issue occurs when a product does not meet its specification?

Select an answer
Question 40

What is the purpose of the quality review technique?

Select an answer
Question 41

Which of the following are PRINCE2 principles? Select all that apply.

Select an answer
Question 42

Which of the following are PRINCE2 themes? Select all that apply.

Select an answer
Question 43

Which of the following are PRINCE2 processes? Select all that apply.

Select an answer
Question 44

Which of the following are members of the project board? Select all that apply.

Select an answer
Question 45

Which of the following are appropriate risk responses for threats? Select all that apply.

Select an answer
Question 46

Which of the following are management products in PRINCE2? Select all that apply.

Select an answer
Question 47

Which of the following should be considered when tailoring PRINCE2? Select all that apply.

Select an answer
Question 48

PRINCE2 is a prescriptive method that must be applied in exactly the same way to every project.

Select an answer
Question 49

The PRINCE2 quality theme defines the quality management approach and how products will be reviewed.

Select an answer
Question 50

The Senior User represents the interests of the suppliers.

Select an answer
Question 51

The project board can authorize an exception plan when tolerances are forecast to be exceeded.

Select an answer
Question 52

PRINCE2 requires a project to be divided into management stages.

Select an answer
Question 53

The PRINCE2 principle that says a project should be adapted to its environment is ___.

Question 54

The project board role that owns the business case is the ___.

Question 55

The document that records threats and opportunities is the ___ register.

Question 56

The PRINCE2 process that verifies acceptance and recommends project closure is ___.

Question 57

The report produced at the end of each stage is the ___ report.

Question 58

Match each PRINCE2 theme to its focus.

Question 59

Match each PRINCE2 process to its main purpose.

Question 60

Match each management product to its description.