Latihan Pengurusan Projek PMP

Latih 80 soalan asal PMP merangkumi kumpulan proses, kekangan, nilai perolehan, risiko, pihak berkepentingan, kualiti dan kaedah agile.

Tahap: PMP Kesukaran: intermediate 80 soalan 60 min
Jawab setiap soalan pengurusan projek, kemudian semak markah. Jawapan salah disimpan setempat untuk ulang kaji.
Hari berturut-turut: 0 hari Disimpan hanya pada peranti ini
Kemajuan 0 / 80
Soalan 1

What is a project?

Pilih jawapan
Soalan 2

What is project management?

Pilih jawapan
Soalan 3

Which three constraints are traditionally shown in the project management triangle?

Pilih jawapan
Soalan 4

Who typically approves the project charter?

Pilih jawapan
Soalan 5

What is a project charter?

Pilih jawapan
Soalan 6

Which process group defines the project and identifies initial stakeholders?

Pilih jawapan
Soalan 7

Which process group develops detailed project plans?

Pilih jawapan
Soalan 8

Which process group coordinates resources to perform the project work?

Pilih jawapan
Soalan 9

Which process group tracks progress and applies corrective action?

Pilih jawapan
Soalan 10

Which process group finalizes activities and hands off the deliverables?

Pilih jawapan
Soalan 11

What is a work breakdown structure (WBS)?

Pilih jawapan
Soalan 12

What is a work package?

Pilih jawapan
Soalan 13

What is the critical path?

Pilih jawapan
Soalan 14

What does float (slack) measure?

Pilih jawapan
Soalan 15

If an activity has zero float, what does that mean?

Pilih jawapan
Soalan 16

What is planned value (PV)?

Pilih jawapan
Soalan 17

What is earned value (EV)?

Pilih jawapan
Soalan 18

What is actual cost (AC)?

Pilih jawapan
Soalan 19

What does a cost performance index (CPI) below 1 indicate?

Pilih jawapan
Soalan 20

What does a schedule performance index (SPI) below 1 indicate?

Pilih jawapan
Soalan 21

What is a project risk?

Pilih jawapan
Soalan 22

What is a risk register?

Pilih jawapan
Soalan 23

What is risk appetite?

Pilih jawapan
Soalan 24

Which risk response reduces the probability or impact of a threat?

Pilih jawapan
Soalan 25

Which risk response eliminates a threat by changing the project plan?

Pilih jawapan
Soalan 26

Which risk response shifts the impact of a risk to a third party?

Pilih jawapan
Soalan 27

Which risk response acknowledges a risk without taking action?

Pilih jawapan
Soalan 28

Who is accountable for managing a specific risk response?

Pilih jawapan
Soalan 29

What is a stakeholder?

Pilih jawapan
Soalan 30

What is stakeholder engagement?

Pilih jawapan
Soalan 31

What is a RACI matrix?

Pilih jawapan
Soalan 32

In a RACI matrix, who is ultimately answerable for completion of a task?

Pilih jawapan
Soalan 33

What is a change control board (CCB)?

Pilih jawapan
Soalan 34

What is a change request?

Pilih jawapan
Soalan 35

What is a baseline?

Pilih jawapan
Soalan 36

What is scope creep?

Pilih jawapan
Soalan 37

What is gold-plating?

Pilih jawapan
Soalan 38

What is a requirement?

Pilih jawapan
Soalan 39

What does a requirements traceability matrix do?

Pilih jawapan
Soalan 40

What is a milestone?

Pilih jawapan
Soalan 41

What is rolling wave planning?

Pilih jawapan
Soalan 42

What does a burndown chart show?

Pilih jawapan
Soalan 43

What is a sprint in Scrum?

Pilih jawapan
Soalan 44

What is a product backlog?

Pilih jawapan
Soalan 45

Who owns the product backlog in Scrum?

Pilih jawapan
Soalan 46

Who facilitates Scrum events and removes impediments?

Pilih jawapan
Soalan 47

What is servant leadership?

Pilih jawapan
Soalan 48

Which conflict resolution approach seeks a win-win solution?

Pilih jawapan
Soalan 49

In Tuckman model, which stage is the initial orientation phase of a team?

Pilih jawapan
Soalan 50

What is quality assurance?

Pilih jawapan
Soalan 51

What is quality control?

Pilih jawapan
Soalan 52

Why is prevention preferred over inspection?

Pilih jawapan
Soalan 53

Which contract type places the most cost risk on the seller?

Pilih jawapan
Soalan 54

Which contract type places the most cost risk on the buyer?

Pilih jawapan
Soalan 55

What is a procurement statement of work?

Pilih jawapan
Soalan 56

What is the project management plan?

Pilih jawapan
Soalan 57

What is a lessons learned register?

Pilih jawapan
Soalan 58

What is configuration management?

Pilih jawapan
Soalan 59

What is an assumption log?

Pilih jawapan
Soalan 60

What is a project sponsor?

Pilih jawapan
Soalan 61

Which of the following are project management process groups? Select all that apply.

Pilih jawapan
Soalan 62

Which of the following are common project constraints? Select all that apply.

Pilih jawapan
Soalan 63

Which of the following are earned value management components? Select all that apply.

Pilih jawapan
Soalan 64

Which of the following are risk response strategies for threats? Select all that apply.

Pilih jawapan
Soalan 65

Which of the following are Scrum roles? Select all that apply.

Pilih jawapan
Soalan 66

Which of the following are created during project initiation? Select all that apply.

Pilih jawapan
Soalan 67

Which of the following are quality management activities? Select all that apply.

Pilih jawapan
Soalan 68

Which of the following are contract types? Select all that apply.

Pilih jawapan
Soalan 69

Type the longest sequence of dependent activities that determines project duration: ___ path.

Soalan 70

Type the earned value component that measures budgeted cost of work performed: ___ value.

Soalan 71

Type the document that formally authorizes the project: project ___.

Soalan 72

Type the risk response that changes the plan to eliminate a threat: ___.

Soalan 73

Type the Scrum role that owns the product backlog: ___ owner.

Soalan 74

Type the agile chart that shows remaining work over time: ___ chart.

Soalan 75

Match each project management process group to its purpose.

Soalan 76

Match each project artifact to its description.

Soalan 77

Match each earned value term to its description.

Soalan 78

Match each risk response to its description.

Soalan 79

Match each Scrum element to its description.

Soalan 80

Match each quality concept to its description.