PMP 项目管理练习题

通过 80 道原创题练习 PMP,覆盖过程组、约束、挣值、风险、干系人、质量与敏捷方法。

等级: PMP 难度: intermediate 80 道题 60 分钟
回答每道项目管理题,然后查看得分。错题会保存在本机供复习。
连续学习: 0 天 仅保存在此设备
进度 0 / 80
题目 1

What is a project?

选择一个答案
题目 2

What is project management?

选择一个答案
题目 3

Which three constraints are traditionally shown in the project management triangle?

选择一个答案
题目 4

Who typically approves the project charter?

选择一个答案
题目 5

What is a project charter?

选择一个答案
题目 6

Which process group defines the project and identifies initial stakeholders?

选择一个答案
题目 7

Which process group develops detailed project plans?

选择一个答案
题目 8

Which process group coordinates resources to perform the project work?

选择一个答案
题目 9

Which process group tracks progress and applies corrective action?

选择一个答案
题目 10

Which process group finalizes activities and hands off the deliverables?

选择一个答案
题目 11

What is a work breakdown structure (WBS)?

选择一个答案
题目 12

What is a work package?

选择一个答案
题目 13

What is the critical path?

选择一个答案
题目 14

What does float (slack) measure?

选择一个答案
题目 15

If an activity has zero float, what does that mean?

选择一个答案
题目 16

What is planned value (PV)?

选择一个答案
题目 17

What is earned value (EV)?

选择一个答案
题目 18

What is actual cost (AC)?

选择一个答案
题目 19

What does a cost performance index (CPI) below 1 indicate?

选择一个答案
题目 20

What does a schedule performance index (SPI) below 1 indicate?

选择一个答案
题目 21

What is a project risk?

选择一个答案
题目 22

What is a risk register?

选择一个答案
题目 23

What is risk appetite?

选择一个答案
题目 24

Which risk response reduces the probability or impact of a threat?

选择一个答案
题目 25

Which risk response eliminates a threat by changing the project plan?

选择一个答案
题目 26

Which risk response shifts the impact of a risk to a third party?

选择一个答案
题目 27

Which risk response acknowledges a risk without taking action?

选择一个答案
题目 28

Who is accountable for managing a specific risk response?

选择一个答案
题目 29

What is a stakeholder?

选择一个答案
题目 30

What is stakeholder engagement?

选择一个答案
题目 31

What is a RACI matrix?

选择一个答案
题目 32

In a RACI matrix, who is ultimately answerable for completion of a task?

选择一个答案
题目 33

What is a change control board (CCB)?

选择一个答案
题目 34

What is a change request?

选择一个答案
题目 35

What is a baseline?

选择一个答案
题目 36

What is scope creep?

选择一个答案
题目 37

What is gold-plating?

选择一个答案
题目 38

What is a requirement?

选择一个答案
题目 39

What does a requirements traceability matrix do?

选择一个答案
题目 40

What is a milestone?

选择一个答案
题目 41

What is rolling wave planning?

选择一个答案
题目 42

What does a burndown chart show?

选择一个答案
题目 43

What is a sprint in Scrum?

选择一个答案
题目 44

What is a product backlog?

选择一个答案
题目 45

Who owns the product backlog in Scrum?

选择一个答案
题目 46

Who facilitates Scrum events and removes impediments?

选择一个答案
题目 47

What is servant leadership?

选择一个答案
题目 48

Which conflict resolution approach seeks a win-win solution?

选择一个答案
题目 49

In Tuckman model, which stage is the initial orientation phase of a team?

选择一个答案
题目 50

What is quality assurance?

选择一个答案
题目 51

What is quality control?

选择一个答案
题目 52

Why is prevention preferred over inspection?

选择一个答案
题目 53

Which contract type places the most cost risk on the seller?

选择一个答案
题目 54

Which contract type places the most cost risk on the buyer?

选择一个答案
题目 55

What is a procurement statement of work?

选择一个答案
题目 56

What is the project management plan?

选择一个答案
题目 57

What is a lessons learned register?

选择一个答案
题目 58

What is configuration management?

选择一个答案
题目 59

What is an assumption log?

选择一个答案
题目 60

What is a project sponsor?

选择一个答案
题目 61

Which of the following are project management process groups? Select all that apply.

选择一个答案
题目 62

Which of the following are common project constraints? Select all that apply.

选择一个答案
题目 63

Which of the following are earned value management components? Select all that apply.

选择一个答案
题目 64

Which of the following are risk response strategies for threats? Select all that apply.

选择一个答案
题目 65

Which of the following are Scrum roles? Select all that apply.

选择一个答案
题目 66

Which of the following are created during project initiation? Select all that apply.

选择一个答案
题目 67

Which of the following are quality management activities? Select all that apply.

选择一个答案
题目 68

Which of the following are contract types? Select all that apply.

选择一个答案
题目 69

Type the longest sequence of dependent activities that determines project duration: ___ path.

题目 70

Type the earned value component that measures budgeted cost of work performed: ___ value.

题目 71

Type the document that formally authorizes the project: project ___.

题目 72

Type the risk response that changes the plan to eliminate a threat: ___.

题目 73

Type the Scrum role that owns the product backlog: ___ owner.

题目 74

Type the agile chart that shows remaining work over time: ___ chart.

题目 75

Match each project management process group to its purpose.

题目 76

Match each project artifact to its description.

题目 77

Match each earned value term to its description.

题目 78

Match each risk response to its description.

题目 79

Match each Scrum element to its description.

题目 80

Match each quality concept to its description.