سؤال 1
What is a project?
A project is temporary and creates a unique product, service, or result. Daily operations are ongoing, and departments or reports are not projects.
سؤال 2
What is a project manager responsible for?
The project manager leads planning, execution, and control to deliver within scope, time, cost, and quality. They do not approve all purchases, write all code, or hire everyone.
سؤال 3
What is a stakeholder?
Stakeholders include anyone with interest or influence over the project. Sponsors are one group, and tools or phases are not stakeholders.
سؤال 4
What is a program?
A program coordinates related projects to achieve benefits. A single task, meeting, or budget is not a program.
سؤال 5
What is a portfolio?
A portfolio is an organization-level collection of projects and programs. A plan, report, or register is not a portfolio.
سؤال 6
What is a project charter?
The charter authorizes the project and defines high-level scope, objectives, and sponsor. Schedules, risk logs, and agendas come later.
سؤال 7
What is a business case?
A business case explains the costs, benefits, and rationale. Status reports, lessons learned, and team lists are different documents.
سؤال 8
What is a project constraint?
Constraints limit what the project can do, commonly scope, schedule, cost, quality, resources, and risk. Stakeholders, deliverables, and milestones are not constraints.
سؤال 9
What is a deliverable?
Deliverables are tangible outputs of project work. Meetings, budgets, and risks are not deliverables.
سؤال 10
Match each project management term to its meaning.
A project is temporary, a program groups projects, a portfolio is strategic, and stakeholders are affected parties.
سؤال 11
What are project phases?
Phases divide the project into stages such as initiation, planning, execution, and closing. Budget categories, roles, and risk types are different.
سؤال 12
What happens during project initiation?
Initiation defines objectives, stakeholders, and authorization. Execution completes work, closing finalizes, and lessons are archived at the end.
سؤال 13
What happens during project planning?
Planning creates schedules, budgets, risk plans, and communication plans. Authorization happens in initiation and work happens in execution.
سؤال 14
What happens during project execution?
Execution produces deliverables according to the plan. Approval is initiation, closing finalizes, and lessons are captured throughout.
سؤال 15
What happens during monitoring and controlling?
Monitoring and controlling compares actual progress to the plan and applies changes. Authorization and stopping work are not monitoring.
سؤال 16
What happens during project closing?
Closing completes deliverables, archives documents, and captures lessons. Authorization starts the project, and adding scope is change.
سؤال 17
What is a phase gate?
Phase gates review deliverables and decide whether to continue. Constraints, stakeholders, and risks are not gates.
سؤال 18
What is a milestone?
Milestones mark important schedule points with zero duration. Budget lines, team members, and risk responses are different.
سؤال 19
What is a work breakdown structure?
A WBS breaks deliverables into manageable work packages. Stakeholders, agendas, and risks are separate.
سؤال 20
Match each project process group to its purpose.
Initiation authorizes, planning defines, execution performs, and closing finalizes.
سؤال 21
What is project scope?
Scope defines the work and boundaries of the project. Budget, team size, and sponsor are separate.
سؤال 22
What is a requirement?
Requirements describe needed capabilities or conditions. Risks, milestones, and reports are not requirements.
سؤال 23
What is a Gantt chart?
Gantt charts display tasks, durations, and dependencies over time. Risk registers, communication plans, and budgets are different.
سؤال 24
What is the critical path?
The critical path is the longest sequence of dependent tasks. Short tasks, risk responses, and stakeholders are not the critical path.
سؤال 25
What is an estimate?
Estimates forecast effort, time, or cost. Invoices are actual costs, and meetings or deliverables are not estimates.
سؤال 26
What is a project budget?
The budget is the approved cost plan. Task lists, stakeholder analyses, and milestones are different.
سؤال 27
What is a baseline?
Baselines are approved scope, schedule, and cost plans. Risks, meetings, and deliverables are not baselines.
سؤال 28
What is change control?
Change control evaluates, approves, and documents changes. Adding scope without review is scope creep, and deleting plans is not control.
سؤال 29
What is scope creep?
Scope creep happens when requirements grow without control. Risk responses, phase gates, and stakeholders are different.
سؤال 30
Match each scheduling concept to its meaning.
Critical path determines duration, baseline is approved plan, budget is planned cost, and scope creep is uncontrolled growth.
سؤال 31
What is a project resource?
Resources include people, equipment, and materials. Meetings, risks, and deliverables are not resources.
سؤال 32
What is a project risk?
Risks are uncertain events with positive or negative impact. Completed tasks, milestones, and budgets are not risks.
سؤال 33
What is risk mitigation?
Mitigation lowers likelihood or impact. Ignoring risks, deleting logs, or adding scope are not mitigation.
سؤال 34
What is project quality?
Quality measures conformance to requirements and fitness for use. Cost, meetings, and team size are not quality definitions.
سؤال 35
What is a defect?
A defect is nonconformance or failure. Stakeholders, milestones, and resources are not defects.
سؤال 36
What is a RAID log?
A RAID log tracks risks, assumptions, issues, and dependencies. Agendas, budgets, and status reports are separate.
سؤال 37
What is an issue?
Issues are current problems, while risks are future uncertainties. Milestones and deliverables are not issues.
سؤال 38
What is an assumption?
Assumptions are accepted as true for planning. Completed tasks, risk responses, and stakeholders are not assumptions.
سؤال 39
What is a dependency?
Dependencies define how tasks relate, such as finish-to-start. Team members, meetings, and budget lines are not dependencies.
سؤال 40
Match each project document to its purpose.
Risks are future uncertainties, issues are current problems, dependencies link tasks, and RAID logs track items.
سؤال 41
What is a communication plan?
Communication plans define information distribution. Schedules, budgets, and risk logs are different.
سؤال 42
What is a status report?
Status reports communicate progress, issues, and next steps. Stakeholders, milestones, and deliverables are not reports.
سؤال 43
What is a meeting agenda?
Agendas list meeting topics and time. Risk responses, budgets, and work packages are not agendas.
سؤال 44
What is stakeholder analysis?
Stakeholder analysis evaluates needs, interest, and influence. Status reports, charts, and risk logs are different.
سؤال 45
What is escalation?
Escalation moves unresolved issues to higher authority. Deleting issues, adding scope, or ending meetings are not escalation.
سؤال 46
What is a lessons learned document?
Lessons learned capture experience for future projects. Charters, budgets, and stakeholder lists are different.
سؤال 47
What is a kickoff meeting?
Kickoff meetings align the team and stakeholders at the start. Closing meetings, reports, and risk reviews are different.
سؤال 48
What is a retrospective?
Retrospectives inspect team process and improvement. Charters, charts, and budgets are not retrospectives.
سؤال 49
Match each communication concept to its purpose.
Communication plans define sharing, status reports update progress, escalation raises issues, and retrospectives improve.
سؤال 50
What is a decision log?
Decision logs record decisions and reasoning for future reference. Risk registers, Gantt charts, and stakeholder lists are different documents.
سؤال 51
What is Agile project management?
Agile delivers in small increments with feedback. One-time plans, budgets, and stakeholder lists are not Agile.
سؤال 52
What is a sprint?
Sprints are short, timeboxed iterations. Phase gates, risks, and deliverables are different.
سؤال 53
What is a product backlog?
The backlog contains prioritized requirements and work. Reports, budgets, and stakeholder analyses are not backlogs.
سؤال 54
What is a Scrum Master?
The Scrum Master removes impediments and facilitates Scrum. They do not write all code, sponsor, or act as the customer.
سؤال 55
What is a Product Owner?
The Product Owner represents value and prioritizes the backlog. Developers build work, Scrum Masters facilitate, and sponsors fund.
سؤال 56
What is a daily standup?
Standups are brief daily syncs. Charters, risk registers, and budgets are not standups.
سؤال 57
What is a burndown chart?
Burndown charts display remaining effort in a sprint. Stakeholder lists, budgets, and Gantt charts are different.
سؤال 58
What is a Kanban board?
Kanban boards visualize tasks and WIP limits. Agendas, risk logs, and charters are not Kanban boards.
سؤال 59
What is a hybrid project approach?
Hybrid approaches blend predictive and Agile practices. Only waterfall, only Scrum, or no planning are not hybrid.
سؤال 60
Match each Agile concept to its purpose.
Sprints are iterations, backlogs list work, standups are brief meetings, and Kanban boards visualize workflows.